Your opening-week calendar has apartments ready for keys and another phase still under construction. A contractor says the electrical work is complete. Leasing needs to know which residents can start service. Accounting needs to know which bills stay with the owner. Give each question its own answer before treating the utility handoff as complete.
What changes for utility accounts during lease-up?
Lease-up is when a new building starts filling with residents. For utility planning, track the move from construction to occupied apartments. Where residents open individual utility accounts, that includes a billing handoff from the builder or owner. Record whether permanent service is ready. Track the resident's account start separately.
This guide proposes a work process. It isn't a national utility checklist. Con Edison's owner guide says timing depends on how complex the work is, permits and site conditions. Coordination with the utility also matters. Its cost guide also points to how much power you need and work on utility systems. Ask for a project-specific schedule and cost estimate.
Start by confirming how the building is metered and who will pay each account. Don't assume every meter begins with the builder or eventually moves to a resident. House accounts and central services need their own treatment. Master-metered, submetered and owner-paid arrangements need a different billing review.
Ask your utility and lawyer for help where needed with lease terms and splitting bills among residents. For affordable housing, also ask about utility allowances, which account for utilities residents pay. This workflow doesn't show authority to switch an account or charge a resident.
How do you move from construction to permanent service?
Ask the utility to confirm the construction path before promising a permanent-service date. Track temporary service, finished wiring and a permanent meter with power as separate steps.
PSE&G's New Jersey installation guidance asks customers to consult a representative before installation, preferably during planning. Its application covers temporary service as well as new construction. That doesn't show an automatic conversion between them.
For work in phases, PSE&G asks what unit types each phase has, how many and when they'll be ready. It also asks how much power the equipment served by each new electric meter will need. Use that list to discuss each phase with the construction team. Its commercial application covers apartment projects with more than three homes. It also covers mixed-use buildings. That application type doesn't set every meter's rate class.
Separate local approval from utility work
PSE&G requires a local inspection and Certificate of Approval, or cut-in card, before its scheduled service date. Confirm who requests that inspection and who sends the approval to the utility. These are PSE&G New Jersey instructions; another utility may use a different process.
Con Edison's service-update guide gives another example with its own scope. The service layout sets who does the work and the technical requirements. The contractor prepares and completes a readiness checklist before the utility inspects. Final connections and meter installation come later. Ask which steps apply to your project. This upgrade guide doesn't set construction rules for the whole country.
Who holds each account before the first move-in?
Assign responsibility account by account. The table below is our suggested register, with examples to adapt to your building. The utility and your actual agreements determine account setups.
Scroll sideways to see all columns →
| Account or stage | Suggested person in charge | Billing question | Record to keep |
|---|---|---|---|
| Temporary construction service | Authorized construction lead | Who carries service during this phase? | Utility confirmation of temporary-service scope |
| Permanent house and common-area service | Owner's authorized representative | Which accounts remain owner-paid? | Meter/account list and service confirmation |
| Vacant, individually metered apartments | Owner's authorized representative | Is service active, and is landlord enrollment available? | Keep separate proof of activation and enrollment. |
| Resident-paid apartment at move-in | Site team coordinates with the resident | When does the resident's utility account start? | Record the unit, confirmed start date and open issues. |
| Model apartment changing use | Named operations lead | Does the billing arrangement change with occupancy? | Agree when the handoff happens. Keep an updated account record. |
Check landlord enrollment and activation separately
Con Edison's Leave on for Landlord FAQ requires a non-residential account with other units in the building. This is an account outside the home-service class. Recently started accounts must become active before enrollment. Ask the utility to confirm your eligibility and enrolled units.
Enrollment won't automatically activate an unused meter. Con Edison directs owners to Customer Service for that request. Its FAQ also says the program's non-residential accounts have a minimum monthly charge. It applies even when there's no use. Ask about carrying costs before budgeting vacant units as costless.
Our guide to the electric account at move-in explains each stage of the account handoff. It covers both owner and resident accounts.
How do you manage the first wave of move-ins?
Use one working register for construction readiness and account exceptions. Suppose your team plans 30 move-ins in a week. Your building's lease-up pace may differ. The point is to avoid resolving every account from memory at the key desk.
Name the decision-makers. Record the authorized construction contact, owner account contact and site coordinator. Give each open item someone who can act on it.
Confirm each phase. Ask the utility which inspections, approvals, connections and meter work remain. Keep its confirmed dates beside your proposed occupancy dates.
Check the account list. Separate house, model, vacant-unit and resident-paid accounts. Match unit identifiers to the utility's records before requesting changes.
Prepare resident handoffs. Where residents open their own accounts, send setup instructions before move-in. Use the confirmed service date as the check, and keep unresolved starts visible.
Review exceptions before keys. Keep construction delays, inactive meters and incomplete account starts as separate issues. Assign a next action and confirm any changed date with the people affected.
Reconcile after the wave. Compare the account register with service confirmations and bills. Investigate an unexpected owner charge against the unit and dates before deciding what happened.
What if power is ready but the account isn't?
Keep the two statuses separate and ask the utility what remains for that unit. Physical readiness doesn't answer the billing question. An account request also doesn't replace construction confirmation. Our resident setup playbook covers the communication work before move-in day.
The utility examples in this guide were checked November 8, 2026. Reconfirm the current instructions for your project before relying on them.
How Public Grid handles the resident handoff
A lease-up team needs a clear way to handle resident accounts while construction work continues. Public Grid gives each property a move-in link you can send to incoming residents. We set up the resident's utility account so it moves off the owner.
From the property page, managers can use Send move-in link and paste resident emails. The portal shows unit statuses and a start service date per unit. Compare those dates with your move-in list. Follow up on accounts still in progress.
Public Grid is free for owners, property managers and residents. Enter the property's address to check electricity coverage, then use the property's move-in link for the applicable resident accounts.
Common questions
Does pre-leasing mean permanent electric service is ready?
No. Treat leasing progress and utility readiness as separate checks. Con Edison's project guidance separates contractor preparation, inspection and final connection. Confirm the actual service milestone for your building before using a planned move-in date as evidence that power is ready.
Should a model apartment's utility account move to a resident?
Review it when the model becomes an occupied apartment. In our suggested account list, name who handles that change and when they should act. Keep model and common-area accounts separate from resident handoffs, and confirm the actual metering and billing arrangement with your utility.
Does a landlord utility agreement turn on unused meters?
Not at Con Edison. Its Leave on for Landlord FAQ says enrollment doesn't activate unused meters. Contact its Customer Service to request activation, and check program eligibility. A minimum monthly charge can apply to the program's non-residential accounts even without usage.