Boston BERDO
for apartment buildings

Boston’s Building Emissions Reduction and Disclosure Ordinance (BERDO) requires yearly energy and water reports. You also need verification, an independent check of your report, when required. Emissions limits cap the gases released by energy use. Those limits start in 2025 or 2030, depending on your building’s group. [1, 2, 3]

Last verified Nov 10, 2026 · 7 official sources

Next ordinary report
May 15, 2027

2026 energy and water data

Residential coverage
≥15 units

Qualifying parcels can combine buildings

Nonresidential coverage
≥20,000 ft²

Confirm mixed-use classification with the City

Emissions start
2025 / 2030

35+ residential units / 15–34 units; confirm cohort

Alternative payment
$234/tCO2e

Per excess metric ton; separate from fines

Default net zero
2050 onward

Approved pathways can change the applicable result

For a step-by-step guide for owners, read Boston BERDO for apartment owners.

On this page

Check your building. Confirm coverage.

Coverage can follow floor area, residential units or qualifying parcels.

  1. 01

    Check the building and tax parcel.

    Compare use, unit count and floor area to the covered list. Multiple buildings on a parcel can be covered by their combined units/area even if each is small. The ordinance's residential parcel definition includes single ownership. Condo associations and co-op boards can be the owner. [1, 2, 4]

  2. 02

    Confirm classification and reporting entity.

    City guidance treats mixed-use buildings or parcels as residential if homes make up 50% or more of gross floor area. Parking is excluded. The ordinance’s definition for individual residential buildings says more than 50%. Ask the City if your building is exactly 50%. Shared systems may need campus reporting or combined IDs. Shared water alone does not mean the energy systems are shared. [1, 2, 4]

  3. 03

    Confirm the first emissions year and pathway.

    The August 2026 Guide groups residential buildings and majority-residential parcels by unit count, regardless of floor area. Those with 35+ units start in 2025. Those with 15–34 units start in 2030. Nonresidential and majority-nonresidential parcels start in 2025 at 35,000 ft², or 2030 at 20,000–34,999 ft². Check your assigned cohort, or start-year group, with the City if the ordinance’s floor-area rules point elsewhere. [2, 4]

Prepare the record. Complete the filing.

Yearly reporting and third-party verification have different requirements.

  1. 01

    Confirm property facts.

    Check BERDO ID, parcel, use, units, area, reporting entity and any approved flexibility measure. New construction enters after its first full calendar year following the earlier temporary/permanent occupancy certificate. [4]

  2. 02

    Collect all energy and water.

    Include central/common meters and known separately metered tenant energy. Residential tenants have no ordinance duty to report their usage to owners. Request utility aggregates and reconcile their coverage with other records. [2, 3]

  3. 03

    Resolve missing data.

    Missing data has a specific estimation rule for each month, energy type and building use. You need actual data for at least 50% of that use. For unknown areas only, multiply known-area average energy per ft² × missing area × 150%. This is called extrapolation. Otherwise, use current City policy defaults. Mark data that is unavailable or estimated this way. You cannot simply leave apartments out. [3, 7]

  4. 04

    Calculate the correct emissions standard and response.

    Start with the standard for the building's largest primary use. Eligible mixed-use properties may combine standards for their different uses. Evaluate reductions, qualifying renewable measures and alternative compliance payments (ACPs), payments that address excess emissions. Also check any approved portfolio, schedule or hardship measure. Use the City's compliance-year emissions factors. [1, 2, 4]

  5. 05

    Arrange required independent verification.

    Have your first reporting year verified. The 2025 emissions cohort verifies 2025 data in 2026. The 2030 cohort verifies 2030 data in 2031 and skips scheduled 2026 verification, subject to first-year duties. Later scheduled checks happen every five years and cover the prior five years. Your verifier must hold an approved active credential. They must be independent of owner/manager staff and must not have prepared the report. Changes in primary use can trigger an extra check between scheduled years. [3, 4]

  6. 06

    Submit both components and retain evidence.

    Complete both Portfolio Manager and the BERDO Reporting Form. Have the report independently checked when required. Include any required records for measures used to address emissions. Yearly reporting for 2026 is due May 15, 2027. Preserve records ten years. On sale, required data transfers to the new owner; ownership notice is due within 30 days. [1, 3, 4]

Your next deadlines

  1. December 31, 2026

    2025 emissions: qualifying RECs

    Retire qualifying RECs used for 2025 emissions; late-retirement proof must be supplied within 30 days and no later than December 31. Late-purchase proof has a separate 30-day rule. [4]

  2. May 1, 2027

    2026 emissions: named flexibility routes

    Building Portfolio, Individual Compliance Schedule and Short-Term Hardship applications for 2026 emissions are due. Confirm the specific pathway with the City. [1, 5]

  3. May 15, 2027

    Annual reporting

    Yearly reporting for 2026 energy/emissions data. [1]

  4. 2030 / 2031

    Smaller residential cohort

    Smaller cohort begins emissions standards in 2030; 2030 data is reported/verified in 2031. [3, 4]

  5. 2050 onward

    Default emissions standard

    Default Table 1 emissions standard reaches zero. [2]

Past deadlines and rule changes
  1. November 10, 2026

    2027 reporting and application dates published. [1]

  2. October 31, 2026

    City's MA Class I REC Connector Program purchase deadline, distinct from general REC retirement/proof requirements. [5]

  3. September 14, 2026

    Current policies adopted, including default-data methodology. [6, 7]

  4. June 30, 2026

    Last eligible REC generation date in the Guide's example for 2025 emissions. [4]

  5. May 13, 2026

    Current regulations adopted. [6]

  6. 2026

    Report and verify 2025 data for the 2025 cohort. [3]

  7. 2025

    First emissions-standard year for the larger cohort; first default multifamily period begins. [2, 4]

Multifamily limits. By reporting period.

Multifamily limits. By reporting period.
PeriodLimit · kg CO2e/ft²/year
2025–20294.1
2030–20342.4
2035–20391.8
2040–20441.1
2045–20490.6
2050 onward0

These yearly emissions-intensity limits measure gases released per square foot, in kg CO2e/ft²/year. CO2e means carbon dioxide equivalent; kg means kilograms. ACP payment rates use metric tons instead. The first row applies only to buildings already in the emissions program. It does not move the 2030 group’s start date earlier. Default use classes and approved flexibility can change your result. [2, 4]

Senior-living, care and campus uses may have a different classification. [2, 4, 7]

Emissions payments. Separate from fines.

An alternative compliance payment (ACP) addresses excess emissions. Daily violation fines have separate triggers.

Example; unadjusted

Assume a 100,000-ft² multifamily building confirmed in the 2025 cohort, using the default 2025–2029 standard. Verified emissions after eligible other mitigation are 430 metric tons. This assumes correct factors and data, no approved alternative schedule and no other mitigation. [2, 4, 5]

Area × default limit
100,000 × 4.1 kg/ft²
Annual allowance
410,000 kg = 410 tCO2e
Excess emissions
430 − 410 = 20 tCO2e
Current ACP rate
20 × $234
$4,680 ACP

This calculation gives a $4,680 alternative compliance payment. Reporting and emissions violations have separate fines.

Daily residential reporting fines are $300 for the larger tier and $150 for the smaller tier. Daily emissions fines are $1,000 and $300, respectively. The ordinance’s larger tier starts at 35 units or 35,000 gross ft². The smaller tier starts at 15 units or 20,000 ft² below the larger thresholds. The regulations use strict greater-than signs. Ask the City which fine tier applies if the size tests or boundary wording differ. Your unit-based emissions start group does not set your fine tier. [2, 3]

Unresolved differences found during verification can trigger $1,000–$5,000. Hiding emissions noncompliance can also trigger emissions penalties. Before assessing these fines, the City gives notice and 30 days to correct the issue. Fixing it within that period prevents assessment under these rules. It does not extend reporting deadlines. Emissions violations may count for every day of the compliance year and later days left uncorrected. [2, 3]

The current ACP is $234 per excess metric ton CO2e and can mitigate any energy source. The rate is reviewed every five years. [2, 5]

Choose a pathway. Confirm the conditions.

  1. 01

    Reductions and renewable electricity

    Qualifying on-/off-site measures, Boston Community Choice Electricity (BCCE), eligible renewable energy certificates (RECs) and qualifying power purchase agreements have distinct conditions. BCCE Green 100 electricity receives zero-emissions treatment for electricity consumed on enrolled accounts; owner enrollment does not establish resident-account enrollment. RECs address electricity, while ACPs can mitigate any energy source. [2, 4, 5]

  2. 02

    Blended standards

    Eligible primary uses can be combined by floor area. [1, 4]

  3. 03

    Building Portfolios

    Approved multi-building compliance uses a portfolio-level standard; it is distinct from automatic parcel coverage. [2, 4]

  4. 04

    Individual Compliance Schedules

    Eligible owners can seek a customized timeline based on historical emissions. [4]

  5. 05

    Hardship plans

    You must qualify and get approval. Affordable housing is not automatically exempt. Most flexibility measures need Review Board approval. A full-calendar-year vacancy designation can remove verification and emissions duties for that year. Reporting is still required. Regular tenant turnover does not count as that designation. [4]

Bring resident-paid usage to your reporting team.

Include resident-paid energy when preparing your building's BERDO record.

With each resident's permission, Public Grid collects actual monthly in-unit usage where property data sharing is allowed and we handle the resident's account. We export that usage for ENERGY STAR Portfolio Manager, GRESB and BPS or benchmarking reporting. You or your consultant submit the report.

Public Grid is free for owners, managers and residents. Enter your property's address to check electricity coverage.

Unit 305Active

Bills received

STATEMENTUSAGE
Sep 15, 2026Aug 14 – Sep 12471 kWh
Aug 14, 2026Jul 15 – Aug 13618 kWh

BERDO FAQ

Bring your data questions.

We can help you check electricity coverage and the resident-paid usage available for your reporting team.

Book a demoExplore the blog
Does every apartment building start emissions limits in 2025?

No. City guidance puts residential buildings/majority-residential parcels with 35+ units in 2025 and 15–34 in 2030, regardless of area. Confirm the assigned cohort where records conflict. [4]

Do smaller covered buildings report before 2030?

Yes. Yearly reporting is separate from the later emissions start date. [1, 3]

When is the next annual report due?

Annual reports for 2026 data are due May 15, 2027. May 1 applies to Building Portfolio, Individual Compliance Schedule and Short-Term Hardship applications. [1]

Is an ACP the same as a penalty?

No. The current $234-per-excess-metric-ton ACP is a compliance mechanism. Daily violation fines have separate triggers and amounts. [2, 5]

Can we omit tenant-paid energy?

No. Known tenant usage belongs in the report, with prescribed estimation where whole-building data is missing. Residential tenants themselves have no ordinance duty to provide bills to owners. [2, 3]

Does an owner's green electricity plan cover residents?

Zero-emissions BCCE treatment follows electricity consumed on enrolled accounts. Confirm residents' accounts separately. [4]

Does a recent verified report avoid all future verification?

No. First-reporting-year, cohort, five-year and certain use-change requirements apply. Assign an independent qualified verifier who did not prepare the report. [3, 4]

Can an affordable building claim an automatic hardship exemption?

No. Flexibility measures have conditions, most require Review Board approval, and a request alone does not establish relief. [4]