Check your building's assigned energy target or accepted improvement plan. Montgomery County covers most buildings at least 25,000 gross square feet. Owners must report energy use each year and meet their assigned performance standard or an accepted plan. [1, 2, 3, 4, 5, 6, 7]

Last verified Nov 10, 2026 · 8 official sources

Who is covered

≥25,000 gross ft²[1, 3]

Main duty

Benchmark and improve[1, 2, 3]

Next deadline

June 1, 2027[1, 2, 3]

Default multifamily energy target
37 kBtu/ft²/year

The assigned target can differ after adjustments. [2, 6]

Required reduction cap

30% of baseline[2, 6]

Multifamily evaluations

2030/2035 or 2031/2036[2, 3]

On this page

Which buildings does Montgomery County cover?

Montgomery County’s Department of Environmental Protection (DEP) runs the county program.

  1. 01

    Check the inclusive 25,000-ft² threshold and building boundary.

    Some structures count together if they share energy meters, heating or cooling systems, or indoor common areas. Independent spaces may be treated differently. These have their own meters and systems, with no connected indoor space. [1, 3]

  2. 02

    Find your building use and group.

    Multifamily buildings of 250,000 ft² and above are Group 4. Those from 25,000 to below 250,000 ft² are Group 5. Check your exact group in DEP's inventory. Its table uses shortened ranges that overlap. Some mainly industrial/process, infrastructure and open public-assembly uses may qualify for exemption. [1, 3]

  3. 03

    Check the Covered Buildings Inventory/map and performance lookup.

    A building missing from the list is not automatically exempt. Check its area and layout, then contact DEP to correct the record. [2, 3]

Prepare your Montgomery County filing

  1. 01

    Confirm the Montgomery Building ID, cohort, baseline and targets.

    Look up your Montgomery Building ID, group, baseline and targets in DEP's tool. The baseline is the starting point used to measure progress. Claim the right building in the County Benchmarking Portal. [1, 2, 3]

  2. 02

    Gather building details and monthly energy use.

    Include tenant spaces, common areas, all fuels and energy generated on-site. Request combined utility totals, called aggregates, early. [4]

  3. 03

    Fill in Portfolio Manager and get data checked when due.

    Your first report, then every third year, needs a check by a verifier with a recognized credential. Check your building's verification year. Choose someone whose credential DEP recognizes. [1]

  4. 04

    Submit the annual report to DEP through its current portal workflow by June 1.

    Keep your underlying Portfolio Manager record and fix any flagged issues. You must also complete the County submission. Creating the property record alone is not enough. [1]

  5. 05

    Meet the performance standard or submit a BPIP.

    The performance path uses energy from the evaluation calendar year. Report it by June 1 the next year. If you need a BPIP, it is due 90 days before that June 1 deadline. It needs a qualified ASHRAE Level 2 audit, cost-effective measures and a schedule for doing the work. [2]

  6. 06

    Keep records and follow through each year.

    Keep benchmarking each year. With an accepted BPIP, you must also report progress each June 1 and complete work on time. [1, 2]

Your next deadlines

  1. May 1, 2027

    Annual waiver requests

    Annual waiver application, on the annual schedule; not an automatic extension. [1]

  2. June 1, 2027

    Annual benchmarking

    2026 annual benchmark, on the annual schedule. [1, 3]

  3. December 31, 2028 / June 1, 2029

    County / Groups 1–2: interim

    End of earliest County/Groups 1–2 interim evaluation year; following report deadline. [2, 3]

  4. December 31, 2030 / June 1, 2031

    Group 4 multifamily: interim

    Group 4 large-multifamily interim year closes / reporting. [2, 3]

  5. December 31, 2031 / June 1, 2032

    Group 5 multifamily: interim

    Group 5 multifamily interim year closes / reporting. [2, 3]

  6. December 31, 2035 / June 1, 2036

    Group 4 multifamily: final

    Group 4 final evaluation year closes / reporting. [2, 3]

  7. December 31, 2036 / June 1, 2037

    Group 5 multifamily: final

    Group 5 final evaluation year closes / reporting. [2, 3]

Past deadlines and rule changes
  1. October 1, 2025

    HB49/Chapter 844 general effective date; state-law certification/waiver mechanism for qualifying county programs. [8]

  2. February 25, 2025

    Council approved Executive Regulation 17-23AM. [7]

  3. July 31, 2022

    Bill effective, ninety days after signing. [7]

  4. May 2, 2022

    Executive signed Bill 16-21. [7]

  5. April 19, 2022

    County Council passed Bill 16-21. [7]

Include resident-paid energy and all meters that count

  1. 01

    Request whole-building totals

    DEP requires monthly energy use from both common-area and tenant meters. Include electricity, gas, fuel oil or diesel, delivered fuels and renewable generation where they apply. County benchmarking does not require water or waste meters. DEP says five or more meters can qualify for combined data without tenant permission. Four or fewer requires tenant permission. Utility rules count tenants and accounts differently. For example, Potomac Edison has a fewer-than-five-tenant rule. Ask your utility which count applies. [4]

  2. 02

    Include resident-paid energy

    Pepco and BGE use EUDS. Washington Gas uses its Benchmarking Portal and needs gas meter numbers. Potomac Edison uses FirstEnergy's benchmarking tool. Its UBID is different from the County ID. Some data arrives quickly, but DEP warns requests can take 3–4 weeks or longer near deadlines. Cover every calendar day, which sometimes needs thirteen bills. Report on-site solar, parking and EV energy correctly so DEP can make the right adjustments. [4]

  3. 03

    Reconcile each meter once.

    Compare resident-paid records with utility totals and common-area meters. Fill gaps without counting the same energy twice.

The County's adjusted energy target

The County's adjusted energy target
RuleValue
Normalized net site EUI37 kBtu/ft²/year

The type-table value of 37 is not every apartment building's assigned target. Mixed-use floor areas can change the final standard. The required drop from baseline is also capped at 30%. Group 4 evaluates in 2030/2035; Group 5 in 2031/2036. Reports are due the following June. Ask DEP to confirm your group if you are at a size boundary. [2, 3, 6]

How the County adjusts the target

  1. 01

    Maximum required reduction

    The required drop is capped at 30% of baseline. Ask DEP to confirm your final assigned standard. [6]

  2. 02

    Interim standard

    The interim standard is halfway between your baseline and final standard. Use your building's own baseline and adjusted final target. [6]

Montgomery County's payments and penalties

Example: three citations

Assume an apartment building gets one initial citation and two repeat citations. This example assumes three citations. It does not assume an automatic fine each day. [5]

Initial citation
$500
Repeat citations
2 × $750 = $1,500
$2,000 excluding court or other sanctions

This assumes one initial and two repeat citations. Court remedies and other sanctions are separate.

DEP's current guidance lists Class A civil fines: $500 for an initial violation and $750 for a repeat. Each day a violation continues is a separate offense. A citation may seek an abatement order, a court order to fix the problem. Further court sanctions can follow. State law allows higher penalties, but that does not create a new local schedule. DEP says the County Council would need to adopt changes. [5]

Check relief and other ways to meet the rules

  1. 01

    Meet the adjusted standard

    Reach the building-specific adjusted standard and continue annual reporting. [3]

  2. 02

    Submit an improvement plan

    For a BPIP, complete an ASHRAE Level 2 audit. Choose cost-effective measures and set dates and triggers for the work. Get the plan accepted, do the work and report progress. [2, 7]

  3. 03

    Special building types and a second plan

    Some designated building types use the program's ten-year measure-payback rule. This rule concerns how long energy savings take to cover an improvement's cost. It includes affordable housing, common-ownership communities, rent-stabilized multifamily, nonprofit and local small-business buildings. These types are not automatically exempt. A second BPIP for the final deadline has another condition. You must complete specified first-plan measures with payback of five years or less. [2, 7]

  4. 04

    Exemptions, annual waivers and extensions

    Benchmark exemptions and yearly waivers are different. An exemption can remove covered status. Waivers for financial distress, qualifying occupancy, new construction or demolition last one year. Apply by May 1. You can also apply for an extension up to thirty days beyond June 1. Further extensions may be considered for documented extenuating circumstances. [1]

Bring resident-paid usage to your reporting team.

Include resident-paid usage in the whole-building record used for county benchmarking and performance reporting.

With each resident's permission, Public Grid collects actual monthly in-unit usage where property data sharing is allowed and we handle the resident's account. We export that usage for ENERGY STAR Portfolio Manager, GRESB and BPS or benchmarking reporting. You or your consultant submit the report.

Public Grid is free for owners, managers and residents. Enter your property's address to check electricity coverage.

Unit 305Active

Bills received

STATEMENTUSAGE
Sep 15, 2026Aug 14 – Sep 12471 kWh
Aug 14, 2026Jul 15 – Aug 13618 kWh

Montgomery County BEPS questions

Need help with in-unit data?

Talk with our team about resident permission, usage records and reporting exports.

Book a demoExplore the blog
What is Montgomery County BEPS?

It requires yearly energy reporting and verification. You must also meet your building's phased performance targets or follow an accepted improvement plan. [1, 2]

Does it cover multifamily?

Yes. Most buildings at least 25,000 gross ft² are covered. Large and smaller multifamily buildings have separate evaluation groups. [3]

Is every apartment target 37 EUI?

No. The type-table value is 37. Mixed-use floor areas and the 30% baseline cap can change your building's final standard. [2, 6]

When must an apartment building meet BEPS?

Group 4 evaluates in 2030/2035; Group 5 in 2031/2036. Reports are due June 1 the next year. Keep benchmarking each year now. [2, 3]

Do tenants have to give permission for aggregate usage?

DEP generally says five or more meters can use combined totals without permission. Smaller counts need permission. Check your utility's counting rule. [4]

Do I also file Maryland state BEPS?

DEP's current guidance says County buildings follow County rules instead of duplicate state benchmarking and BEPS. Under HB49, state treatment depends on county certification and yearly data transfer. Ask MDE and DEP which certification and waiver apply to your property. [1, 2, 8]

GET STARTED

Check your property’selectricity coverage.

Enter your property’s address to check electricity service.